Dates of disruption
IN PROGRESS PHASE 15 - NEXT PLANNED PHASES - PHASE 16 - PHASE 18
Download the Traffic Management Plan for this street:
DownloadWorks permit ID: PHASE 13 - START DATE 26.09.2024 - 06.10.2024 - PERMIT CL910SWL2304-05-K-02 - IN PROGRESS
Latest Updates
Date
Update
23.05.2024
New High Voltage Electric Supplies into the Hospital Complex
Our client are undertaking a project which requires new 11kV circuits to be routed into the Hospital Complex, a large section of these works will be installed along Hills Road. We have been in consultation with the local authority to plan the works and permission has now been granted to commence.
BRM have been engaged to undertake the civil or installation works and have appointed GTM to manage the traffic management element of the works
All phased TM Plans are attached and available for download as a pack
We will be undertaking a total of 19 Phased works along Hills Road which will be undertaken in stages once the individual Permits are approved by the Local Authority.
13.06.2024 -
PHASE 7 - 03.06.2024 - 09.06.2024. -HAS BEEN COMPLETED - PHASE 7 PERMIT CL910SWL2304-05-A-02
13.06.2024 -
PHASE 8 - 10.06.2024 - NEW END DATE 17.06.2024 - PARTIAL COMPLETION TO BE REVISITED - PHASE 8 PERMIT CL910SWL2304-05-B1-02
04.07.2024
PHASE 9 - NEW START DATE 17.06.2024 - 30.06.2024 - PARTIAL COMPLETION TO BE REVISTED - PHASE 9 PERMIT CL910SWL2304-05C-02
14.07.2024
PHASE 2 - NEW START DATE 01.07.2024 - 14.07.2024 - .PHASE 2 PERMIT CL910SWL2304-05D-02 - COMPLETE
12.08.2024
PHASE 1 - START DATE 23.07.2024 - 09.08.32024 - PHASE 1 PERMIT CL910SWL2304-05-I-02 - COMPLETE
12.08.2024
PHASE 3 - START DATE 12.08.2024 - 25.08.2024 - PHASE 3 PERMIT CL910SWL2304-05-J-02 - COMPLETE
02.09.2024
PHASE 4 - START DATE 2608.2024 - 01.09.2024 - PHASE 4 PERMIT CL910SWL2304-05-N-02 - PARTIAL COMPLETION TO BE REVISITED
16.09.2024
PHASE 11 - START DATE 02.09.2024 - 15.09.2024 - PHASE 11 PERMIT CL910SWL2304-05-E-02 - COMPLETE
26.09.2024
PHASE 12 - START DATE 16.09.2024 - 26.09.2024 - PHASE 12 PERMIT CL910SWL2304-05-F-02 - COMPLETE
07.10.2024
PHASE 13 - START DATE 26.09.2024 - 06.10.2024 PHASE 13 PERMIT CL910SWL2304-05-K-02 - COMPLETE
07.10.2024
PHASE 15 - START DATE 07.10.2024 - 13.10.2024 PHASE 15 PERMIT CL910SWL2304-05-G-02 -IN PROGRESS
26.09.2024
PHASE 16 - START DATE 14.10.2024 - 20.10.2024 PHASE 16 PERMIT CL910SWL2304-05-H-02 - PLANNED
26.09.2024
PHASE 18 - START DATE 21.10.2024 - 27.10.2024 PHASE 18 PERMIT CL910SWL2304-05-M-02 - PLANNED
Contact us
If you have any further questions regarding this construction work, or the disruption caused, please get in touch with us.